Your company recently changed suppliers to reduce the lead time to 8 days. The g
ID: 452623 • Letter: Y
Question
Your company recently changed suppliers to reduce the lead time to 8 days. The goal of this change is to improve the CSL while maintaining the current safety stock of 100 units. Your company uses a continuous review system. The daily demand is 25 units. If your current inventory position is 250 units, how much should you order? 0 50 100 150 200 300 400 The EOQ amount Which of the following is NOT a common concern for suppliers who have a JIT partnership? Long-term contracts of JIT partnerships can limit flexibility. Decreased utilization and capacity as a result of reducing setup times. Reduced order sizes often prevent benefits from economies of scale. Need for excess finished goods inventory. Strict quality assurance.Explanation / Answer
option D is right answer.
JIT system does not encourages excess finished goods inventory
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.