Baya Power owns 25 small power generating plants. It has contracted with Yaguez
ID: 451663 • Letter: B
Question
Baya Power owns 25 small power generating plants. It has contracted with Yaguez Services to overhaul the power turbines of each of the plants. All the turbines are similar and an 80% learning curve is appropriate. The number of hours that Yaguez billed Baya to complete the second turbine was 460. Baya pays Yaguez $60 per hour for its services. As the maintenance manager for Baya, you are trying to answer the following: The estimated cost of overhauling the first six turbines. The "steady-state" cost of manufacturing a turbine (You have to find out the asymptotic hours of making "many" turbines, as illustrated in class?Explanation / Answer
TN=T1C
T6=(460 hours)( .562)
= 258.52 Hours
(258.52 Hours)($60/hour)
= $15511.2
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.