PLEASE SHOW WORK SO I CAN FOLLOW ALONG--THANKS! The following table contains inf

ID: 451369 • Letter: P

Question

PLEASE SHOW WORK SO I CAN FOLLOW ALONG--THANKS!

The following table contains information regarding jobs that are to be scheduled through one machine:

OPERATIONS TIME

JOB

PROCESSING TIME(DAYS)

DUE DATE

A

4

20

B

12

30

C

2

15

D

11

16

E

10

18

F

3

5

G

6

9

1.) What is the shortest operating time (SOT) schedule (sequence)?

2.) What is the slack time remaining (STR) schedule (sequence)?

3.) For the schedule (sequence) F-G-C-D-E-A-B, compute mean flow time?

OPERATIONS TIME

JOB

PROCESSING TIME(DAYS)

DUE DATE

A

4

20

B

12

30

C

2

15

D

11

16

E

10

18

F

3

5

G

6

9

Explanation / Answer

Shortest operating time (SOT) schedule is the order of work where highest preference is given to the job with shortest operating time. Accordingly, mean flow time is calculated.

JOB

PROCESSING TIME(DAYS)

DUE DATE

Flow Time

C

2

15

0+2=2

F

3

5

2+3 = 5

A

4

20

5+4=9

G

6

9

9+6=15

E

10

18

15+10=25

D

11

16

25+11=36

B

12

30

36+12=48

Mean Flow time = (2+5+9+15+25+36+48)/7 = 20 days

2. (STR)

Slack time remaining = Due date time remaining – Processing time

JOB

PROCESSING TIME(DAYS)

DUE DATE

Slack

A

4

20

20-4=16

B

12

30

30-12=18

C

2

15

15-2 = 13

D

11

16

16-11=5

E

10

18

18-10 = 8

F

3

5

5-3 = 2

G

6

9

9-6 = 3

On the basis of slack time remaining , following sequence will be followed.

JOB

PROCESSING TIME(DAYS)

DUE DATE

Slack

F

3

5

2

G

6

9

3

D

11

16

5

E

10

18

8

C

2

15

13

A

4

20

16

B

12

30

18

3.

For the Job Sequence of F-G-C-D-E-A-B

JOB

PROCESSING TIME(DAYS)

DUE DATE

Flow Time

F

3

5

0+3 = 3

G

6

9

3+6 = 9

C

2

15

9+2 = 11

D

11

16

11+11=22

E

10

18

22+10=32

A

4

20

32+4=36

B

12

30

36+12=48

Mean flow time =(3+9+11+22+32+36+48)/7   = 23 days

JOB

PROCESSING TIME(DAYS)

DUE DATE

Flow Time

C

2

15

0+2=2

F

3

5

2+3 = 5

A

4

20

5+4=9

G

6

9

9+6=15

E

10

18

15+10=25

D

11

16

25+11=36

B

12

30

36+12=48