The budgeted cost of a project is $863,000, however, the actual cost of implemen

ID: 449250 • Letter: T

Question

The budgeted cost of a project is $863,000, however, the actual cost of implementation was $857,800. The data in the table which follows gives the budgeted and actual cost information of each phase of the project. a) For each activity, calculate the Quantity Variance = (Actual Quantity - Budgeted Quantity) times Budgeted Price b) For each activity, calculate the Price Variance = (Actual Price - Budgeted Price) times Actual Quantity c) Identify the two main factors which accounted for the difference between actual and budgeted costs.

Explanation / Answer

a) Activity qty variance Phase 1 (60-50)*100 1000 Phase 2 (10-4)*2000 12000 Phase 3 (80-100)*500 -10000 Phase 4 (80-80)*10000 0 b) Activity Phase 1 (120-100)*60 1200 Phase 2 (2500-2000)*10 5000 Phase 3 (520-500)*80 1600 Phase 4 (9800-10000)*80 -16000 c) Activity in Phase 1 & phase 2 are the major reason behind increase in cost They used higher qty and cost more than the budget leading to hike in actual cost of implementation

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote