PROJECT MANAGEMENT QUESTION Geoff coolly surveyed his earned value table at the

ID: 449069 • Letter: P

Question

PROJECT MANAGEMENT QUESTION

Geoff coolly surveyed his earned value table at the conclusion of month 24. It was hard to believe that two short years ago, with his membership at Match.com about to expire, he had managed to craft an ad to catch the eye of divine Miss Smylie. Now he was almost done making this critical project. Some might think him crass for taking such an approach but he practiced what he preached at the small commuter school where he taught. Calculate the Schedule Performance Index and the Cost Performance Index for this project (costs are in dollars in the table). What is the estimated time to completion for this project? How much is the estimated cost for completion of this project? Comment on Geoff’s skills as a project manager.

Activity

4

8

12

16

20

24

28

Total

% Complete

Courtship

1000

2000

3000

3000

3000

1000

1300

90%

Proposal

500

5000

0

0

5000

10500

100%

Negotiations

500

0

1000

1500

100%

Invitations

800

800

100%

Showers

400

800

800

2000

100%

Musicians

400

1000

1400

20%

Caterers

200

2000

5000

7200

30%

Rehearsal

400

4000

4400

10%

Party

1000

2000

3000

20%

Ceremony

500

500

500

500

3500

5500

20%

Reception

1000

1000

6000

8000

30%

Honeymoon

2000

4000

6000

40%

Total

1000

3000

10700

5900

9700

7500

25500

63300

Cumulative

1000

4000

14700

20600

30300

37800

63300

Actual

2500

5100

12700

6400

10600

9000

0

Cumulative Actual

2500

7600

20300

26700

37300

46300

Activity

4

8

12

16

20

24

28

Total

% Complete

Courtship

1000

2000

3000

3000

3000

1000

1300

90%

Proposal

500

5000

0

0

5000

10500

100%

Negotiations

500

0

1000

1500

100%

Invitations

800

800

100%

Showers

400

800

800

2000

100%

Musicians

400

1000

1400

20%

Caterers

200

2000

5000

7200

30%

Rehearsal

400

4000

4400

10%

Party

1000

2000

3000

20%

Ceremony

500

500

500

500

3500

5500

20%

Reception

1000

1000

6000

8000

30%

Honeymoon

2000

4000

6000

40%

Total

1000

3000

10700

5900

9700

7500

25500

63300

Cumulative

1000

4000

14700

20600

30300

37800

63300

Actual

2500

5100

12700

6400

10600

9000

0

Cumulative Actual

2500

7600

20300

26700

37300

46300

Explanation / Answer

Activity

4

8

12

16

20

24

28

Total

% Complete

Earned Value

Schedule Performance Index (SPI) = EV / PV

Courtship

1000

2000

3000

3000

3000

1000

1300

90%

1170

0.90

Proposal

500

5000

0

0

5000

10500

100%

10500

1.00

Negotiations

500

0

1000

1500

100%

1500

1.00

Invitations

800

800

100%

800

1.00

Showers

400

800

800

2000

100%

2000

1.00

Musicians

400

1000

1400

20%

280

0.20

Caterers

200

2000

5000

7200

30%

2160

0.30

Rehearsal

400

4000

4400

10%

440

0.10

Party

1000

2000

3000

20%

600

0.20

Ceremony

500

500

500

500

3500

5500

20%

1100

0.20

Reception

1000

1000

6000

8000

30%

2400

0.30

Honeymoon

2000

4000

6000

40%

2400

0.40

Total

1000

3000

10700

5900

9700

7500

25500

63300

25350

0.40

Cumulative

1000

4000

14700

20600

30300

37800

63300

Actual

2500

5100

12700

6400

10600

9000

0

Cumulative Actual

2500

7600

20300

26700

37300

46300

Cost Performance Index (Budgeted Cost / Actual Value)

0.40

0.59

0.84

0.92

0.92

0.83

Total time for the completion of the project is 28 months.

Estimated Cost for the completion of the project is 63300.

As a project manager, Geoff’s skills are not very good. Though, he has planned the program efficiently from the courtship to the final marriage and reception. He has also made sure that the people get enough time from starting the courtship to the final marriage. The actual spending is far from the budgeted, as a project manager, he will have to align the costs with the actual spending that are incurred.

Activity

4

8

12

16

20

24

28

Total

% Complete

Earned Value

Schedule Performance Index (SPI) = EV / PV

Courtship

1000

2000

3000

3000

3000

1000

1300

90%

1170

0.90

Proposal

500

5000

0

0

5000

10500

100%

10500

1.00

Negotiations

500

0

1000

1500

100%

1500

1.00

Invitations

800

800

100%

800

1.00

Showers

400

800

800

2000

100%

2000

1.00

Musicians

400

1000

1400

20%

280

0.20

Caterers

200

2000

5000

7200

30%

2160

0.30

Rehearsal

400

4000

4400

10%

440

0.10

Party

1000

2000

3000

20%

600

0.20

Ceremony

500

500

500

500

3500

5500

20%

1100

0.20

Reception

1000

1000

6000

8000

30%

2400

0.30

Honeymoon

2000

4000

6000

40%

2400

0.40

Total

1000

3000

10700

5900

9700

7500

25500

63300

25350

0.40

Cumulative

1000

4000

14700

20600

30300

37800

63300

Actual

2500

5100

12700

6400

10600

9000

0

Cumulative Actual

2500

7600

20300

26700

37300

46300

Cost Performance Index (Budgeted Cost / Actual Value)

0.40

0.59

0.84

0.92

0.92

0.83