The following costs have been estimated for the activities in a project
A) Develop a cost shedule based on earliest start times
B) Delovop a cost schedule based on lastest start
C) Suppose that it has been determined that the 6,000 dollars for activity G is not evenly spread over the 3 weeks. Instead, the cost for the first week is 4,000 and the cost is 1,000 per week for each of the last 2 weeks. Modify the cost schedule based on earlier start times to reflect this situation?
Activity Immediate precedessors time cost a --------- 8 8000 b ------------ 4 12000 c A 3 6000 D B 5 15000 E C,D 6 9000 F C,D 5 10000 G F 3 6000Explanation / Answer