This project has seven activities. Examine the table below:
Activity
Preceding Activities
Optimistic
(o)
Most Likely
(m)
Pessimistic
(p)
A
-
6
7
8
B
-
6
9
14
C
A
7
9
11
D
A
5
10
12
E
C, B
7
10
12
F
D
8
8
11
G
E, F
5
8
10
1. Use the variance given and comute the number of days that gives the project manager a 95% chance of completing the entire project. Show your work.
2. What will happen if activity F took one day longer than it is estimated to complete?
Activity
Preceding Activities
Optimistic
(o)
Most Likely
(m)
Pessimistic
(p)
A
-
6
7
8
B
-
6
9
14
C
A
7
9
11
D
A
5
10
12
E
C, B
7
10
12
F
D
8
8
11
G
E, F
5
8
10
Explanation / Answer
This project has seven activities. Examine the table below: Activity Preceding A
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.