Slack time in a network is the a. shortest amount of time that could be required

ID: 439153 • Letter: S

Question

Slack time in a network is the a. shortest amount of time that could be required to complete the activity. b. amount of time that an activity can be delayed without delaying the entire project. c. amount of time that you would expect it would take to complete the activity. d. amount of time that an activity would take assuming very unfavorable conditions. e. difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times.

Explanation / Answer

e. difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote