Bragg's Bakery is building a new automated bakery in downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed.
a. Identify the critical path.
b. What is the normal project length?
Normal project length weeks
c. What is the project length if all activities are crashed to their minimum?
Project length weeks
d. Bragg's loses $3,600 in profit per week for every week the bakery is not completed. How many weeks will the project take if we are willing to pay crashing cost as long as it is less than $3,600?
The project will take weeks
ACTIVITY PREDECESSOR NORMAL TIME (WEEKS) CRASH TIME (WEEKS) EXPEDITINGCOST/WEEK A — 6 5 $ 3,500 B A 5 3 3,900 C A 11 8 4,200 D B, C 8 7 2,200 E C 3 2 2,500 F D, E 5 4 4,800
Explanation / Answer
The precedence diagram of activities as follows :
A
B
C
D
E
F
The possible parallel paths and their corresponding Normal durations as follows :
A-B-D-F = 6 + 5 + 8 + 5 = 24 weeks
A-C-D-F = 6 + 11 + 8 + 5 = 30 weeks
A-C-E-F = 6 + 11 + 3 + 5 = 25 weeks
A-C-D-F by having the longest duration is the critical path , Normal project length is same as duration of critical path which is 30 weeks
CRITICAL PATH = A-C-D-F
NORMAL PROJECT LENGTH = 30 WEEKS
Duration of A-B-D-F if all its activities are crashed to maximum = 5 + 3 + 7 + 4 weeks = 19 weeks
Duration of A-C-D-F if all its activities are crashed to maximum = 5 + 8 + 7 + 4 weeks = 24 weeks
Duration of A-C-E-F if all its activities are crashed to maximum = 5 + 8 + 2 + 4 weeks = 19 weeks
The critical path with longest duration is again A-C-D-F and the revised project length 24 weeks
THE PROJECT WILL TAKE 24 WEEKS
Since crashing cost cannot be more than $3600 , following are the options :
Crash activity D by 1 day ( from 8 weeks to 7 weeks ) at a cost of $2200
Crash activity E by 1 day ( 3 weeks to 2 weeks ) at a cost of $2500
Crash activity A by 1 days ( 6 weeks to 5 weeks ) at a cost of $3500
The least cost option is to crash activity D by 1 week at a cost of $2200
The revised project duration i.e. duration of A-C-D-F = 6 + 11 + 7 + 5 weeks = 29 weeks
THE PROJECT WILL TAKE 29 WEEKS