45. CP is determined based on 1. Longest path 2. Shortest path 3. Average path 4

ID: 434449 • Letter: 4

Question

45. CP is determined based on 1. Longest path 2. Shortest path 3. Average path 4. Final path 46. EPC indicates mainly needed: 1. Entertainment sites 2. Restaurants 3. Cruises for top management 4. All the above 5. None of the above 47. SME loans are determined based on: 1. EPC 2. Budget 3. Itemized cost 4. All the above None of the above 5. 48. J-shape lifecycle is mainly used with 1. High quality products 2. Limited number of products 3. Samples not actual product 4. All the above 5. None of the above 49. SME may: 1. 2. 3. Combine controlling departments Never combine controlling departments Cancel controlling departments 4. Outsource all departments 50. SME sustainability may skip: 1. Job satisfaction 2. Training 3. EOE/equity/fairness 4. All the above 5. None of the above

Explanation / Answer

Answering the first 4 questions:

45. CP is determined based on longest path.

Answer: Option 1

46. EPC indicates mainly needed for all of the above

Answer: Option 4

47. SME loans are determined based on all of the above

Answer: Option 4

48. J-shaped lifecycle is mainly used for limited number of products

Answer: Option 2