1)Aggregate planning requires which of the following information? a. forecast of

ID: 434198 • Letter: 1

Question

1)Aggregate planning requires which of the following information?

a. forecast of expected demand

b. inventory costs

c. policies regarding employment levels

d. all of the above

2)Which of the following is not a basic option for altering the availability of capacity?

overtime

hiring & layoffs

part time

d.all of the above

3)these is among the demand options of aggregate planning?

subcontracting

back orders

c)varying work force

d)overtime

4)One way to increase reliability is to:

improve package design

increase the number of service stations

increase the mean time to repair

increase the number of backup components

a.

overtime

b.

hiring & layoffs

c.

part time

d.all of the above

3)these is among the demand options of aggregate planning?

a.

subcontracting

b.

back orders

c)varying work force

d)overtime

4)One way to increase reliability is to:

a.

improve package design

b.

increase the number of service stations

c.

increase the mean time to repair

d.

increase the number of backup components

Explanation / Answer

1.
Correct answer:
(D) All of the above
Reason: It is the type of planning that is having the balanced organization resources and also meets the expected demand; it is used to obtain the levels of employment and inventories over an intermediate range of time.  

2.
Correct answer:
(D) All of the above
Reason: The basic point which is not considering under altering the availability of capacity is INVENTORY, and rests on the listed points are basic capacity options.

3.
Correct answer:
(B) Back-orders
Reason: For aggregate planning, the demand option is back ordering. It is the situations when there require increasing the demand to match up with the capacity.
Pricing, Promotion, Back ordering, and new demand creation are some of the situations.   

4.
Correct answer:
(A)Improve package design
Reason: It is the collection of techniques that are utilized to make changes in the initial design for improving and enhancing the reliability.