C & A furniture uses a four-step process to make a wood table
Process - processing time (minutes)
Milling table top - 10 minutes
Milling table stand - 5 minutes
Assembly - 15 minutes
Finishing - 20 minutes
Part A, use the information above - The milling machine requires a setup time of 30 minutes to make table tops and a changeover time of 30 minutes to make table stands. C&A works an 8-hour day. What is the capacity of the milling machine (in tables per day) if the batch size is 10?
A. 22.86 tables/day
B. 7.05 tables/day
C. 15.32 tables/day
D. 6.40 tables/day
Part B - C&A Printing takes 10 seconds to print a page in color, but after 500 pages, the printer must be cooled down for 15 minutes. No pages can be printed while the printer is cooling down. C&A's demand rate is 3 pages per minute. What is the smallest batch size to ensure the process is demand-constrained?
A. 37
B. 90
C. 64
D. 500
Explanation / Answer
Question:- The milling machine requires a setup time of 30 minutes to make table tops and a changeover time of 30 minutes to make table stands. C&A works an 8-hour day. What is the capacity of the milling machine (in tables per day) if the batch size is 10?
Answer:- A. 22.86 tables/day
Question:- C&A Printing takes 10 seconds to print a page in color, but after 500 pages, the printer must be cooled down for 15 minutes. No pages can be printed while the printer is cooling down. C&A's demand rate is 3 pages per minute. What is the smallest batch size to ensure the process is demand-constrained?
Answer:- B. 90?