Operations Management: Sustainability and Supply Chain Manageme Quiz: Final Exam
ID: 431710 • Letter: O
Question
Operations Management: Sustainability and Supply Chain Manageme Quiz: Final Examination This Question: 4 pts ? https //www.mathxl.com/Student/PlayerTest aspx?testid-1839 ??? Kishan Puran &I; 7/24/186:10 PM Time Remaining: 01:32.09 Submit Qu 5 of 60 (21 completel) This Quiz: 240 pts possible As the production planner tor Xiangling Hu Prodacts, Inc., you have been given a bil of material for a bracket that is made up of a base, 2 springs, and 4 clamps The base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting Each housing has 2 bearings and 1 shaft. Thene is no inventory on Click the loon to view the product structure. Your boss at Xiangling Hu Products, Inc, has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 10. The lead times for the components are bracket (1 week), base (1 week), spring (1 week), clamp (1 week) housing (2 weeks), hande (2 weeka), casting (3 weeks), bearing (1 week), and shaft (1 week) a) Choose the correct time-phased product structure for the bracket O A. ??. O D. harde Tme i n weeks Time i n weeks b) In what week do you need to start the casings? The castngs need to be started in week (enter your response as a whole number), Click to select your answersExplanation / Answer
a. Answer B, because handle has a lead time of 2 weeks and housing has alead time of 2 weeks.
b. Casting needs to be started in 4th week.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.