The project described by:
Activity/ Immediate Predecessor/ Optimistic / Most likely /Pessimistic /Standard Deviation/ Variance
A/ -- / 4 / 5 / 6 / 0.333 / 0.111
B / -- / 12 / 16 / 18 / 1.000 / 1.000
C/ a / 2 / 8 / 14/ 2.000 / 4.000
D / a / 5 / 5 / 5 / 0.000 / 0.000
E / b,c / 6 / 7 / 8 / 0.333 / 0.111
According to Table 12-3, there are five activities in a PERT project. What is the variance of the critical path?
5.222
4.222
1.222
0
1.111
5.222
4.222
1.222
0
1.111
Explanation / Answer
1.222