Evan Schwartz has six jobs waiting to be processed through his machine. Processi

ID: 429445 • Letter: E

Question

Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days) and due date information for each job are as follows:  

Job                            Processing Time                                 Due Date

a                                           2                                                  3

b                                           1                                                  2

c                                           4                                                  12

d                                           3                                                   4

e                                           4                                                    8

f                                            5                                                   10

Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean ow time and mean tardiness of the six jobs under each sequencing rule. Which rule would you recommend? Please show all work. Thank you!

Explanation / Answer

FCFS: Process the jobs in order of their arrival, A, B, C, D, E.

Job

Processing time

Flow time

Due date

Tardiness

a

2

2

3

0

b

1

3

2

1

c

4

7

12

0

d

3

10

4

6

e

4

14

8

6

f

5

19

11

8

55

21

Mean flow time = total flow time/ no. of jobs

                                   = 55/6 = 9.17

Mean Tardiness = total tardiness/ no. of jobs

                                = 21/6 = 3.50

SPT: Sequence the jobs by smallest processing time.

Job

Processing time

Flow time

Due date

Tardiness

b

1

1

2

0

a

2

3

3

0

d

3

6

4

2

c

4

10

12

0

e

4

14

8

6

f

5

19

11

8

53

16

Mean flow time = 53/6 = 8.83

Mean Tardiness = 16/6 = 2.67

SLACK: Sequence the jobs by minimum slack. The slack for each job is calculated as: (due date - today's date) - remaining processing time.

Job

Processing time

Due date

Slack

a

2

3

0

b

1

2

0

c

4

12

7

d

3

4

0

e

4

8

3

f

5

11

5

Job

Processing time

Flow time

Due date

Tardiness

a

2

2

3

0

b

1

3

2

1

d

3

6

4

2

e

4

10

8

2

f

5

15

11

4

c

4

19

12

7

55

16

Mean flow time = 55/6 = 9.17

Mean Tardiness = 16/6 = 2.67

DDATE: Sequence the jobs by earliest due date

Job

Processing time

Flow time

Due date

Tardiness

b

1

1

2

0

a

2

3

3

0

d

3

6

4

2

e

4

10

8

2

f

5

15

11

4

c

4

19

12

7

54

15

Mean flow time = 54/6 = 9

Mean Tardiness = 15/6 = 2.50

Process DDate method is recommended as it has the lowest Mean tardiness.

Job

Processing time

Flow time

Due date

Tardiness

a

2

2

3

0

b

1

3

2

1

c

4

7

12

0

d

3

10

4

6

e

4

14

8

6

f

5

19

11

8

55

21