The following information concerns progress at day 40 of an Internet marketing p

ID: 429318 • Letter: T

Question

The following information concerns progress at day 40 of an Internet marketing project. Determine if the project is in control based on time and cost to date. If not, what is the cost overage or underage ?

Activity

Duration

Budget

Actual
Cost

%
Complete

1-2

10

300

250

100.00

2-3

8

400

450

100.00

2-4

12

350

380

100.00

4-3

0

0

0

3-5

18

405

400

70.00

5-6

16

450

-------

0.00

Activity

Duration

Budget

Actual
Cost

%
Complete

1-2

10

300

250

100.00

2-3

8

400

450

100.00

2-4

12

350

380

100.00

4-3

0

0

0

3-5

18

405

400

70.00

5-6

16

450

-------

0.00

Explanation / Answer

Total budgeted time = 10+8+12+18+16 = 64 days

Activity 3-5 is 70% complete by 40th day. According to budgeted, duration, time it should be taken to complete 70% of activity 3-5:

10+8+12+18x0.70 = 42.60

Budgeted time = 42.60

Actual time = 40 days

Since the actual time taken is less than budgeted time, the project is in control in terms of time.

Budgeted total cost till 70% of activity 3-5 = 300+400+350+405x0.70 = 1333.50

Actual cost                                                             = 250+450+380+400 =1480

Since actual cost is greater than budgeted cost, the project is out of control in terms of cost.

Cost overage = 1480-1333.50 =146.50