65) C&A; makes two flavors of ice cream -chocolate and vanilla. Each gallon is p

ID: 426887 • Letter: 6

Question

65) C&A; makes two flavors of ice cream -chocolate and vanilla. Each gallon is produced and shipped in discrete containers. The demand for the ice cream (in gallons) is given as follow: Day Chocolatea 20 60 30 50 10 Vanilla 40 100 30 70 100 C&A; operates 8 hours a day and 5 days a week. What is the takt time and how would C&A; schedule the production of its ice cream to level demand? A) 5.5 minutes per gallon, alternate between I unit of chocolate and 2 units of vanilla B) 5.5 minutes per gallon, alternate between chocolate and vanilla C) 4.7 minutes per gallon, alternate between I unit of chocolate and 2 units of vanilla D) 4.7 minutes per gallon, alternate between chocolate and vanilla 6) Daily demand for a product is 200 units. The production lead time is 2 days. A 1-day safety sto is kept. How many kanban containers will be needed if one container holds 100 units? A) 2 B) 1 C) 4

Explanation / Answer

Answer:

65.

C) 4.7 minutes per gallon , alternate 1 unit of chocolate and 2 units of vanilla

Explanation:

66.

D) 6

Explanation :