This Question: 1 pt 5 of 8 This Quiz: 8 pts p Hour R HourR Hour R Hour x 1 3.35
ID: 423809 • Letter: T
Question
This Question: 1 pt 5 of 8 This Quiz: 8 pts p Hour R HourR Hour R Hour x 1 3.35 0.65 73.05 0.48 13 3.11 08 19 3.41 1.66 2 3.10 1.13 8 2.75 1.13 14 2.73 1.36 20 2.89 1.14 3 3.12 1.489 3.12 0.66 15 3.12 1.11 21 2.55 1.13 4 3.491.21 10 2.95 1.33 16 2.94 0.55 22 3.38 0.51 5 3.07 1.12 1 2.73 1.12 17 2.96 1.43 23 284 1.58 6 2.86 0.42 12 2.97 0.45 18 2.74 1.34 242.74 1.02 Based on the sampling done, the control limits for 3-sigma x chart are (round all intermediate calculations to three decimal places before procoeding with furthe Upper Control Limit (UCL?)-inches round your response to three decima,places Lower Control Limit (LCL?)-inches round your response to three decimal places). Based on the i-chart, the wire cutting process has been The control timits for the 3-sigma R-chart are (round all intermediate calculations to three decimal places before proceeding with further calculations) Upper Control Limit (UCLR)-inches (round your response to three decimal places) Lower Control Limit (LCLR) inches (round your response to three decimal places) Enter your answer in each of the answer boxesExplanation / Answer
Xbarbar = 2.97
Rbar = 1.03
UCLx = Xbarbar +A2Rbar
LCLx = Xbarbar - A2Rbar
Value of A2 will depend on the sample size.
We assume that the sample size is 5
Then
UCLx = 2.97 + 0.577 x1.03 = 3.56
LCLx = 2.97-0.577x1.03 = 2.38
R limits
UCLR = D4Rbar = 1.03 x2.114 = 2.17
LCLR = D3Rbar =0
It can be seen that with n=5. the process is within limits.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.