Select the right answers Moving to the next question prevents changes to this answer. estion 17 A Corrective Action Request (CAR) has which of the following items on it? Identification of the person responsible for completing the corrective action. identification of the person responsible for the thing the caused the need for the corrective action. (the person who screwed up) A date for projected completion A date the request was made (initiated) A written description of the issue A complete description of what steps should be taken Moving to the next question prevents changes to this answer.Explanation / Answer
A Corrective Action Request will contain all of the details as mentioned in the options, except the last one- ‘ a complete description of what steps should be taken’. As this option does not come under a request, but will come under a Corrective Action Plan or a Solution.
While above all needs to be incorporate to begin or request a corrective plan like what date is request initiated, when the project needs to be completed, and who are the persons involved.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.