Question 2 10 points You are working for an international construction company.
ID: 422188 • Letter: Q
Question
Question 2 10 points You are working for an international construction company. Your project involves pulling together over 13 diflerent subprojects.You are having dilficulty in ensuring three subcontractors are doing their work correctly. As you review the project results, you notice you have spent US $1,200,000 at the last reporting point. You know the schedule is not too bad, since your schedule performance index (SPI) is 1.1. Considering you feel you should have spent US $1,300,00 to this point, what are the cost performance index (CPI), and the schedule and cost variances? 1.19 $230.000, and $230,000) O 1.19, $130,000, and $230,000 1.43, $130,000, and $130,000) 1.1, ($230.000), and $130,000Explanation / Answer
PV=$1,300,000
EV = PV*SPI = 1,300,000*1.1 = $1,430,000.
calculating the CPI = EV/AC
= 1430000/1200000 = 1.19
;
now we calculate SV = EV - PV
= 1430000 - 1300000=130,000
CV = EV - AC
=1430000 - 1200000
=$230,000.
so the answer is option B 1.19, $130,000, and $230,000
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.