A Project plan is required to be prepared for the work tendered below, using Microsoft Project 2000 Software, or later, or any other suitable project software. Notes should accompany the project assignment describing the details and thinking behind the project form. The project should show such features as:

Gantt chart with tasks, dates, bar charts, etc. showing linked tasks with any lead or lag times • critical path • resources list completed • resources usage • task usage 7 • tracking Gantt chart • resource fixed and task costs • project % completion and cost report(s) • tasks that can start simultaneously or prior to the finish of their predecessor, if any.

Task usage with associated costs (resource and task costs) should be simulated for the project at 100 % completion and reports produced. Hard copies of the project assignment are required. CDs or floppy disks can also be submitted. It should be noted that the critical path view must be saved as a separate project or as a screen dump figure pasted into, say, Paint, which is usually available in Microsoft Office (or Word) Programs/Accessories on the Start Menu. This is because, if resources are assigned to tasks the critical path is obscured and shows in normal task colour. Any views that may be lost in the course of completing the project must be saved at an appropriate time. Alternatively students may wish to do a power point presentation of various views of their project.

It is worth using the first task as a repository for making notes about the project as one progresses. This is done by selecting Project/Task Notes which brings up a dialogue box into which can be typed notes and memos, such as “foreman is not assigned to task (a) because this task is performed on the same day as task (b) to which the foreman has already been assigned”, etc. Leaving the resources dialogue box open and assigning resources will leave the same resources selected for repetitive tasks, which facilitates resource assignment. Alternatively, if there are many repetitive tasks, by holding down the ‘Control’ key each repetitive task can be highlighted and then by selecting the Assign Resources icon (or Tools/Assign Resources) and entering the resources data in the dialogue box all the tasks selected will be updated without having to select each task individually. This same technique can be applied to task progress tracking, by holding down the ‘Control’ key each repetitive task can be highlighted and then by selecting Tools/Tracking/Update Task, and entering the progress data (e.g. 100 %, actual duration and remaining duration) all the tasks will be updated without having to select each task individually.

Tender plan

Total material and hiring cost - 18800

Total labour and fixed cost - 18500

Total cost - 37300

Profit margin - 10% - 3730

Total tender cost - 41030

Assumptions used -

Firstly all old and new holes are excavated - 40 holes.

It takes one hour to excavate one hole - 40 manhours

5 people with 8 hour shift are deployed for hole excavation in one day.

Everyday two new lamps are completed and old lamp removed

So it takes 10 days of hiab work

Two lamps of one street are kept working and two are removed every day. So lighting disruption is minimal.

Lamps are purchased and paid for by client

Temporary reinstatement happens every day - 10 days

Permanent reinstatement happens after work of a street is completed - every alternative day - 5 days

Work activity amount rate cost Materials Lanterns 20 10 200 Ballast 20 5 100 Ignitor 20 5 100 Capacitor 20 5 100 Column 20*6*4metre 10.per metre 4800 Cable 20*10 metre 10 2000 Photo electric cell 20*1 50 1000 Tarmac 20*10kg 10 2000 Concrete 20*15kg 10 3000 Hiring charges Crane 10 days 200 per day 2000 Hiab 10 days 300 per day 3000 Concrete mixer 5 days 100 per day 500

Explanation / Answer

The total cost for 40 holes is 40*10 = 400 amount

The hiab work will require 10*200 = 2000 amount

Total cost behind the lamp is 600

Temporaray and permanent reinstatement will cost 1500 amount