A project has four activities (A, B, C, and D) that must be performed sequential
ID: 419607 • Letter: A
Question
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:
Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
Use the random numbers 0.1637, 0.5967, 0.6928 and 0.8154 to simulate the completion time of the project in weeks.
Activity Activity Time
(weeks)
Probability A 4 0.33 5 0.35 6 0.25 7 0.07 B 8 0.18 10 0.56 12 0.26 C 7 0.06 9 0.27 11 0.42 13 0.20 15 0.05 D 9 0.55 11 0.45
Explanation / Answer
Base case = Most likely possible time = 5+10+11+9 = 35 weeks
Worst Case = Most time consuming scenario = 7+12+15+11 = 45 weeks
Best case = 4+8+7+9 = 28 weeks
Activity Random Number Completion Time A 0.1637 6 weeks B 0.5967 10 weeks C 0.6928 12 weeks D 0.8154 9 weeks Total 37 weeksRelated Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.