C&A; makes two flavors of ice cream- chocolate and vanilla. Each gallon is produ
ID: 419048 • Letter: C
Question
C&A; makes two flavors of ice cream- chocolate and vanilla. Each gallon is produced and shipped In discrete contalners. The demand for the ice cream (In gallons) Is given as follow 40) 100 30 70 100 20 30 50 10 C&A; operates 8 hours a day and 5 days a week. What is the takt time and how would C&A; schedule the production of Its ice cream to level demand? 5.5 minutes per gallon, alternate between chocolate and vanilla 5.5 minutes per gallon, alternate between 1 unit of chocolate and 2 units of vanila 4.7 minutes per gallon, alternate between chocolate and vanilla 47 minutes per gallon, alternate between 1 unit of chocolate and 2 units or vanillaExplanation / Answer
4.7 minutes per gallon, alternate between 1 unit of chocolate and 2 units of vanilla
Explanation:
Talk time = Production time available / Weekly demand
C&A company works 8 hours per day * 5 days a week
Total production time available = 8 hour * 5 days = 40 hours per week
8 hours * 60 = 480 minutes per day
Average demand of chocolate per day = (20 + 60 + 30 + 50 + 10) / 5 = 170/5 = 34 gallons per day
Average demand of vanilla per day = (40 + 100 + 30 + 70 + 100)/ 5 = 340 / 5 = 68 gallons per day
Total demand = 34 +68 = 102 gallons
Talk time = 480 / 102 = 4.7
C&A should schedule the production of its ice cream, 1 unit of chocolate and 2 units of vanilla.
Chocolate 34 gallons
Vanilla = 68 gallons
demand = 34 / 68 = 1 / 2 units