· Question 9 To ensure good master scheduling, the master scheduler shoukd do wh
ID: 411309 • Letter: #
Question
· Question 9 To ensure good master scheduling, the master scheduler shoukd do which of the following? a-be involved with costumer order promising b-identify and cornmunicate all problem c-all the above d-never lose sight of the aggregate plan e-be visible to all levels of management Question 10 Which of the following are the inputs files necessary to run an MRP system? a-bill of material (bom)file b-exception report c-planned order schedules d-none all above Question 11 When adding production capacity to a plant which of the following issues should be considered? a-all the above b-use the external capacity c-the frequency of capacity additions d-monitoring system balance e-none of the above Question 12 If you were at an overview of the Majors Operations Planning Activities in most organizations, which of the following planning activities would follow after Aggregate Planning in a manufa a-master production schedules b-material requirement planning c-starter capacity planning d-process planning e-order schedule g operation?Explanation / Answer
9) The correct option is-c) All of the above { Considering other options are placed above All of the above option}
For a good master scheduling, it is very necessary for a master scheduler to take inputs from all levels of management, hence be visible to all levels of management and communicate problems to them. Also, to make a good schedule, a master scheduler should be aware of the customer order processing and aggregate plan. Hence correct option is all of the above.
10) The correct option are - (a) Bom file , (c) planned order schedule & (e) quality management report
To run an MRP, Bill of material is required to identify & quantify the material parts required per unit. Planned order schedule is required to determine the net requirement of resources and quality management report will give an idea of the number of defects or reworks normally required so that the net requirements could be adjusted accordingly.
11) The correct option is: a) all of the above
When adding a new capacity we must consider what would be the balance capacity when new capacity is added, whether we can use external capacity instead of adding a new capacity and if we are to add new capacity, what would be the frequency of capacity additions.
12) The correct option is: a) Master production schedule
After Aggregate planning, the plan is disaggregated and a Master production schedule is formed. The master production schedule is followed by preparing a Material Requirement Planning.
13) The correct option is b) All of the above
In production planning, all the inputs given in the options i.e current physical capacity, current workforce and inventory levels are internal to the firm and must be taken into account in the production planning process.