Use the following Table for questions 4-6 . Year Project A Project B 0 -17500 -1

ID: 409456 • Letter: U

Question

Use the following Table for questions 4-6.

Year

Project A

Project B

0

-17500

-12500

1

2500

7500

2

3500

3500

3

5500

2500

4

3500

1500

5

2000

500

4. Calculate NPV for both projects. Which project would be a better value? (All things equal.) Assume the cost of capital is 14%.

Project A: ________________      Project B: __________________

5. Calculate IRR for both projects. Which project would be a better value? (All things equal.) Assume the cost of capital is 7%

Project A: ________________      Project B: __________________

Year

Project A

Project B

0

-17500

-12500

1

2500

7500

2

3500

3500

3

5500

2500

4

3500

1500

5

2000

500

Explanation / Answer

NPV for Project 1

NPV={(2500/(1+.14)1)+(3500/(1+.14)2)+(5500/(1+.14)3)+(3500/(1+0.14)4)+(2000/(1+0.14)5)}-17500

= 2192.98+2713.17+3716.21+2083.33+1041.66-17500

=-7835.98

NPV for Project 2

NPV{(7500/(1+.14)1)+(3500/(1+.14)2)+(2500/(1+.14)3)+(1500/(1+0.14)4)+(500/(1+0.14)5)}-12500

=6578.94+2713.17+1689.18+892.85+260.41-12500

=-365.45

Her for both projects the NPV values are negative.

NPV for Project 1

NPV={(2500/(1+.14)1)+(3500/(1+.14)2)+(5500/(1+.14)3)+(3500/(1+0.14)4)+(2000/(1+0.14)5)}-17500

= 2192.98+2713.17+3716.21+2083.33+1041.66-17500

=-7835.98

NPV for Project 2

NPV{(7500/(1+.14)1)+(3500/(1+.14)2)+(2500/(1+.14)3)+(1500/(1+0.14)4)+(500/(1+0.14)5)}-12500

=6578.94+2713.17+1689.18+892.85+260.41-12500

=-365.45

Her for both projects the NPV values are negative.