Three products manufactured must be routed through three machines and each has to be processed in the same sequence on each machine: machine 1, machine 2, and finally on machine 3. The times required to perform the work on item i (i=1,2,3) by machine j (j=1,2,3) are given in the following table:
machine1 machine2 machine3
item 1 1 hour 2 hours 3 hours
item 2 2 hours 1 hour 4 hours
item 3 4 hours 2 hours 1 hour
Formulate an integer programming problem to minimize the total time necessary to process all products.
Explanation / Answer
let there be x,y,z amount of items i=1,2,3
total time by machine 1=x+2*y+4*z=a
total time by machine 2=2*x+y+2*z=b
total time by machine 3=3*x+4*y+z=c
optimize (a+b+c)