A construction project is broken down into the 10 activities listed below. A B C

ID: 403801 • Letter: A

Question


A construction project is broken down into the 10 activities listed below.


A B C (A) Activity (B) Preceding Activity (C)Time (weeks)


1 4


2 1 2


3 1 4


4 1 3


5 2,3 5


6 3 6


7 4 2


8 5 3


9 6,7 5


10 8,9 7



A. Draw the precedence diagram.


B. Find the critical path


C. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of 1 week each at a cost of $10,000 per week per activity, which activities would you shorten in order to shorten the project by four weeks?