1. When a company plans a new product development project, which department should impact the decisions? (Points : 5) Sales and MarketingEngineering
Manufacturing
Finance
All of the above
2. Which of the following would NOT be considered part of a company's intellectual property? (Points : 5) Patents
Trademarks
Internally developed software source code.
Industry standards documents.
Proprietary manufacturing processes.
3. In the context of product life cycle management, ECN stands for: (Points : 5) Electronic Component News
Explicit Congestion Notification
Engineering Change Notice
Electrochemical Noise
Eastman Color Negative
4. The key elements of Total Quality Management are: (Points : 5) Customer Involvement
Supplier Quality Management
Process Management
Cross functional product design
All of the above
5. Sun Tzu, the ancient Chinese military philosopher, states that: (Points : 5) The pen is mightier than the sword.
A house divided against itself cannot stand.
You must know your enemy and you must know yourself.
All is fair in love and war.
If you sew the wind, you will reap the whirlwind.
6. Which of the following should NOT be included in a product requirements document? (Points : 5) Size constraints
Operating Environment
Agency approvals
SWOT analysis
Wired or wireless interfaces
7. What are the stages of successful group project progress? (Points : 5) Forming; Storming; Norming; Performing
Intervention; Denial; Acceptance; Rehabilitation
Attention; Interest; Decision; Action
Always; Be; Closing
Introduction; Body; Conclusion
8. Which new product development tasks require a financial investment prior to production? (Points : 5) Product Development
Manufacturing Tooling
Patent Application
Marketing Surveys
All of the above
9. On a Gannt Chart, every task requires these features EXCEPT: (Points : 5) Task prerequisites
Estimated Time of Completion
Resources required
Personnel assigned the task
Estimated cost of the task.
10. Engineering Technologists are expected to operate under a high ethical standard because, (Points : 5) they make so much money.
they are members of professional societies.
they are well educated.
their work impacts public safety.
they are closely monitored by the government.
11. Every Senior Project is expected to have: (Points : 5) an electronic component.
a wired or wireless interface.
a computer or embedded controller.
a positive impact on society.
All of the above.
12. Who are the stake-holders in your senior project? (Points : 5) Yourself.
Your teammates.
Your target customers.
The University
All of the above.
13. Senior management will NOT approve a new product development project that: (Points : 5) is feasible within the work-group's capabilities.
is cost effective in terms of limited company capital.
conflicts with the company's strategic goals.
complies within the industry's standards
satisfies customer requirements.
14. A cloud storage system allows a workgroup: (Points : 5) ubiquitous access to project documents over the Internet.
automatic backup and archiving of controlled documents.
revision control of group documents
editting and revision of documents is possible by all group members.
All of the above.
15. Which of the following is NOT a function of the Senior Project Sequence requirement? (Points : 5) To demonstrate that students can work together in an engineering team.
To show that students can incorporate different skills from their course work into a unique project.
To demonstrate an engineering student's adaptability and problem solving skills.
To refine a student's oral and written communication skills.
To make work to fill the total credit hour requirement.
16. At what stage in a product's life cycle should a Project Manager consider agency approvals? (Points : 5) When the new product's requirements document is first drafted.
After the design phase is complete.
After the product has received acceptance in the market.
After a company receives enough customer requests.
After a court issues a "cease-and-desist" order.
17. It is important to keep an engineering logbook... (Points : 5) to document the configuration under which a test takes place.
to document how and why products fail tests.
to demonstrate project progress to managers.
to jot down project solutions or work-arounds.
All of the above
18. The National Electric Code is written in order to (Points : 5) allow compatibility between appliance manufacturers and power companies.
regulate the energy efficiency of household appliances.
limit the liability of licensed electricians.
reduce the hazards of shock and fire associated with power distribution in commercial buildings and residences.
reduce competition from foreign electronics manufacturers.
19. Companies have legal departments to... (Points : 5) comply with local and national labour laws.
protect intellectual property and patents.
review contracts entered with suppliers and customers.
litigate product liability cases.
All of the above.
20. A group contract should have a conflict resolution plan in order to: (Points : 5) mitigate disputes between group members.
mitigate disputes with the faculty adviser.
mitigate disputes with third party stake holders.
mitigate disputes with law enforcement.
mitigate disputes with the university. 1. When a company plans a new product development project, which department should impact the decisions? (Points : 5)
Explanation / Answer
1.e
2.a
3.d
4.c
5.e
6a
7c
8b
9a
10b
11c
12e
13a
14b
15e
16c
17c
18b
19a
20d