1. The following table shows a four-step process. The necessary time for one wor
ID: 401685 • Letter: 1
Question
1. The following table shows a four-step process. The necessary time for one worker to perform the step on one unit is listed as well as the number of workers at each step.
Step
Description
Process Time (min/unit)
Number of workers
Capacity (units/hr)
Utilization
1
Mold Components
13
3
2
Assemble
7
2
3
Calibrate
9
2
4
Package
4
1
a. Calculate the hourly capacity for each step.
b. What is the capacity of the process as a whole? ________
Step
Description
Process Time (min/unit)
Number of workers
Capacity (units/hr)
Utilization
1
Mold Components
13
3
2
Assemble
7
2
3
Calibrate
9
2
4
Package
4
1
Explanation / Answer
maximize x1+x2+x3+x4 where x1,--x4 are the steps contraints are the process time and workers solving the equations you will get xi --x4 and then u can proceed