https www.math d com Student playerHomework.aspx?homeworkid-501770983&questionide 3&flushede fals add-5156147&cer erwin-yes Secure OMG 322-32 Introduction to Operations Management Sandy Homework: Chapter 3 HW Assignment Score: 0.25 of 1 pt & Problem 3.11b The following is a table of activities associated with a project at Rafay ishfaq's software firm in Chicago, their durations and what activities each must precede 8 of 10 (8 complete) Activity Duration (weeks) Precedes A (start) F (end) This exercise contains only parts b, c, and d b) The activities on the critical path are A-C-F c) The total project completion time for Rafay Ishfaq's software firm is 12 weeks (Enter your response as a whole number) d) Determine the slack time for each of the activities (Enter your responses as whole numbers ) Activity Slack Time (weeks) Enter your answer in the answer box and then click Check Answer Clear A O Type here to searchExplanation / Answer
Th possible paths and their corresponding durations as follows :
A-C-F = 1 + 9 + 2 = 12 weeks
A-B-E-F = 1 + 3 + 5 + 2 = 11 weeks
Out of above , AC-C-F has the longest duration and therefore is the CRITICAL PATH.
Since, the total project completion time is same as duration of the critical path , the project completion time will be 12 weeks
It is to be noted that Slack time for all activities lying on the critical path will be ZERO
Therefore, slack time for activities A/C/F will be ZERO
Slack time for activity B as well as E
= Duration A-C-F – Duration A-B-E-F
= 12 – 11 weeks
= 1 week
ACTIVITY
SLACK TIME ( WEEKS)
A
0
B
1
C
0
E
1
F
0
ACTIVITY
SLACK TIME ( WEEKS)
A
0
B
1
C
0
E
1
F
0