OSCM 3321-Fal 018 Homework: Homework Assignment Chapter 3 45016 (3 complete) Score: 0 of 1 pt Problem 3.8b Roger Ginde n developing a peogram in supply chain management cersfication for activibes, immedate predecessors, and times appear in e accompanying table managers. Ginde has listed a number of activities that must be completed befo 10 A D E.F Ths exercise contains only parts b e, and d b) The critical actvibes for the leadership training program development project are B-D-E-G )The project lungth for the leadership training program development project days Enter your answer in the answer box and then click Check Answer Clear A

Explanation / Answer

a) The various paths and their expected completion time of this project are

So the critical path is B-D-E-G as it has the longest expected completion time of 30 days. Therefore the critical activities are B-D-E-G  

b) The project length for the training program = expected completion time of the critical path = 30 days