1 To get capacity from time between completions you do which mathematical operat
ID: 397108 • Letter: 1
Question
1 To get capacity from time between completions you do which mathematical operation?
a.Multiply times the length of the day
b.Divide by the length of the day
c.Subtract the length of an hour
d.Take the inverse
2 Which of the following are required for a capacity calculation (choose all that apply)
a.Time between process starts Time between process starts
b.Time between process completions Time between process completions
c.Total Time spent in the process Total Time spent in the process
d.Length of the time horizon in question
Explanation / Answer
Answer 1. b. You divide the length of the day by the time between completions to get capacity per day.
Answer 2. a,b,c,d. All these behave as an input for capacity calculation.