You have been serving as Electroscan's project manager and are now well along in the project. Develop a narrative status report for the board of directors of the chain store that discusses the status of the project to date and at completion. Be as specific as you can using numbers given (see attachment) and those you might develop. Remember, your audience is not familiar with the jargon used by project managers and computer software personnel; therefore, some explanation may be necessary. Your report will be evaluated on your detailed use of data, your total perspective of the current status and future status of the project, and your recommended changes (if any).

Electroscan, Inc. 555 Acorn Street, Suite Boston. Massachusetts 29 In-store Scanner Project (thousands of dollars) Actual Progress as of January 1 Name PV EV Scanner project 420 395 47 476 -81 1103 H1.0 Hardware 92 20 260 13 15 25 H 1.1 Hardware specifications (DS) H 1.2 Hardware design (DS) H1.3 Hardware documentation (DOC) H 1.4 Prototypes (PD) H1.5 Test prototypes (T H1.6 Order circuit boards (PD) H 1.7 Preproduction models (PD) 15 25 5 30 10 10 40 30 30 0 150 0 100 100 431 15 OP 1.0 Operating system 196 15 OP 1.1 Kernel specifications (DS) OP 1.2 Drivers 20 45 10 -21 45 31 751 105 OP 1.2.1 Disk drivers (DEV) 37 20 130 25 OP 1.2.2 VO drivers (DEV) OP 1.3 Code software 40 -10 100 OP 1.3.1 Code software (C) 42 OP 1.3.2Documentsoftware(DOC) 45 25 40 30 - OP 1.3.3 Code interfaces C OP 1.3.4 Beta test software U 108 148 21 8 U1.0 Utilities U 1.1 Utilities specifications (DS) U1.2 Routine utilities (DEV) U1.3 Complex utilities (DEV) U 1.4 Utilities documentation (DOC U1.5 Beta test utilities (D 35 150 100 40 10 17 153 49 30 10 46 tem integration 75 -15 1.1 Architecture decisions (DSY S1.2 Integration hard/soft (DEV) 1.3 System hard/software test 45 12 30 14 Project documentation (DOc) Intearation acceptance test S 1.5

Explanation / Answer

The budgeted cost (BAC) of the project is 915, and the EV is 395. Which indicates that roughly 43% (=395/915) of the project work is completed.

SV and CV for the project are negative, indicating that the project is behind schedule as well as over budget.

EAC is 1103, which means that the whole project is going to cost 1103 when completed. So the project will exceed the budgeted cost of 915 at completion.

Except Hardware, all the parts of the project are over budget. However, Utilities and System Integration are ahead of schedule going by their positive SV.