AlwaysRain Irrigation, Inc., would like to determine capacity requirements for t

ID: 393498 • Letter: A

Question

AlwaysRain Irrigation, Inc., would like to determine capacity requirements for the next four years. Currently two production lines are in place for making bronze and plastic sprinklers. Three types of sprinklers are available in both bronze and plastic: 90-degree nozzle sprinklers, 180-degree nozzle sprinklers, and 360-degree nozzle sprinklers. Management has forecast demand for the next four years as follows YEARLY DEMAND Plastic 90 Plastic 180 Plastic 360 Bronze 90 Bronze 180 Bronze 360 1 (IN 000s) 31 13 49 2 (IN 000s) 45 14 56 3 (IN 000s) 56 15 65 4 (IN 000s) 54 19 68 17 13 20 4 10 4 12 15 Both production lines can produce all the different types of nozzles. The bronze machines needed for the bronze sprinklers require three operators and can produce up to 18,000 sprinklers. The plastic injection molding machine needed for the plastic sprinklers requires five operators and can produce up to 295,000 sprinklers. Three bronze machines and only one injection molding machine are available What are the capacity requirements for the next four years? (Assume that there is no learning.) (Enter the demand values in thousands Round your answers to 2 decimal places.) Year 1 Year 2 Year 3 Year 4 Plastic 136 Demand for plastic sprinklers Percentage of capacity used Machine requirements Labor requirements 93 141 Bronze Demand for bronze sprinklers Percentage of capacity used Machine requirements Labor requirements

Explanation / Answer

Given:

YEARLY DEMAND

Product

1

(IN 000s)

2

(IN 000s)

3

(IN 000s)

4

(IN 000s)

Plastic 90

31

45

56

54

Plastic 180

13

14

15

19

Plastic 360

49

56

65

68

Bronze 90

8

7

6

17

Bronze 180

4

4

8

13

Bronze 360

10

12

15

20

Calculations are as follows:

Particulars

Year 1

Year 2

Year 3

Year 4

Plastic

Demand for plastic sprinklers

D

93

115

136

141

No. of molding M/c available

N

1

1

1

1

Capacity per machine per year

C

295

295

295

295

Total Capacity available

TC = N*C

295

295

295

295

Percentage of capacity used

% = D/TC x 100

31.53%

38.98%

46.10%

47.80%

Machine requirements

M = D/TC

0.32

0.39

0.46

0.48

Labor required per machine

L

5

5

5

5

Labor requirements

M x L

1.58

1.95

2.31

2.39

Bronze

Demand for plastic sprinklers

D

22

23

29

50

No. of molding M/c available

N

3

3

3

3

Capacity per machine per year

C

18

18

18

18

Total Capacity available

TC = N*C

54

54

54

54

Percentage of capacity used

% = D/TC x 100

40.74%

42.59%

53.70%

92.59%

Machine requirements

M = D/TC

1.22

1.28

1.61

2.78

Labor required per machine

L

2

2

2

2

Labor requirements

M x L

2.44

2.56

3.22

5.56

YEARLY DEMAND

Product

1

(IN 000s)

2

(IN 000s)

3

(IN 000s)

4

(IN 000s)

Plastic 90

31

45

56

54

Plastic 180

13

14

15

19

Plastic 360

49

56

65

68

Bronze 90

8

7

6

17

Bronze 180

4

4

8

13

Bronze 360

10

12

15

20