Software development projects only have the potential to deliver value after the

ID: 393269 • Letter: S

Question

Software development projects only have the potential to deliver value after the project is delivered to end flow time of a dollar through its application delivery process and has enlisted you to help. Use the project data supplied as part of the quiz directions for your analysis Assumptions users. A large multi-national firm is interested in understanding the Project cost is continuously accumulated. Costs start accumulating at the beginning of the project start date and stop accumulating at the end of the project end date. In other words, the project duration is End Date- Start Date+1 day Project cost is accumulated at a constant rate throughout the project Based on these assumptions, what is the average flow time (in days) of a cost $ for projects that started during the first half of 2009? Round your answer to one decimal place.

Explanation / Answer

During the first half of 2009, only the above mentioned projects were started. The project duration has been calculated as End date - Start date +1 day

The average flow time for a $ in these projects would be

(761 + 820 + 741 + 673) / 4

= 748.8

Release Name Project Start Date Project Finish Date Project duration GL AbXence Tracking INV 1/1/2009 1/31/2011 761 CRE - LeaXe KgKt - XyXtek 1/1/2009 3/31/2011 820 GXI - KeKento Prod 1/5/2009 1/15/2011 741 TripX.net ReturnX upgrade 1/5/2009 3/4/2011 673