The following five jobs, along with their processing time and due dates, are given below.

Job

A

B

C

D

E

Using the shortest processing time (SPT) rule, the average flow time for the five jobs is _____.

more than 5 but less than or equal to 10 days

more than 10 but less than or equal to 15 days

more than 15 but less than or equal to 20 days

less than or equal to 5 days

Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____.

more than 5 but less than or equal to 10 days

more than 15 but less than or equal to 20 days

less than or equal to 5 days

more than 10 but less than or equal to 15 days

Processing Days Due

Job

Time (days) From Today

A

8 12

B

4 9

C

3 6

D

7 7

E

5 20

Explanation / Answer

Using the shortest processing time (SPT) rule,

Sequence the jobs as C-B-E-D-A ( Based on increasing order of processing time)
C 3
B 4+3 = 7
E 5+7 = 12
D 7+12 = 19
A 8+19 = 27
Using the shortest processing time rule, the average flow time = (3+7+12+19+27)/5 = 13.6
Answer: b. more than 10 but less than or equal to 15 days

Using the earliest due date (EDD) rule,

Sequence the jobs as C-D-B-A-E ( Based on increasing order of days due)
C 6
D 7+6 = 13
B 4+13 = 17
A 8+17 = 25
E 5+25 = 30
Using the earliest due time rule, the average flow time = (6+13+17+25+30)/5 = 18.2
Answer: b. more than 15 but less than or equal to 20 days