You are targeting a total Production Volume increase of 10% in the next 7 days c

ID: 392649 • Letter: Y

Question

You are targeting a total Production Volume increase of 10% in the next 7 days compared to the last 7 days' Actual Production Volume Assuming you maintain the same Productivity Rate as last week for the next 7 days, approximately how many Scheduled Hours will you need to schedule to achieve this goal? Home Team Profile Today's Benchmarking Report Headcount Report Report Screen Summary Volume (Packages) Scheduled Hours Overtime Hours Productivity Rate 48.0 51.3 49.5 42.1 47.7 Yesterday Plan Actual Difference Plan Actual Difference Plan Actual Difference 28 44 10 9 6 10 19,000 19,380 380 380 440(60 7 20 (16) Total Prodtivity 86,000 84,881 1,119) ,720 1,726 (6) Team 1 Team 2 Team 3 Team 4 31,000 31,211211 22,500 22,275 -225) 450 440 620 599 21 10 (13) 0 13,500 12,015 1,485) 270 247 -23 5 10,219 13,591 15,827 16,103 Volume (Packages) Scheduled Hours Overtime Hours Productivity Rate 47.3 46.1 50.8 46.0 46.6 Note. The Productivity Report shows Planned, Actual, and Difference from the Plan for Volume in Packages, Scheduled Hours, and Overtime Last 7 Days Plan ActualDifference Plan Actual Difference Plan Actual Difference (68) 217,000 208,320 (-8,680) 4,340 4,428 (88) 70 92 (22) Total Prodtivity 602,000 584,413 17,588) 12,040 12,088 4 196 264 eam Team 2 Team 3 Team 4 Hours. Goal for Productivity Rate is 50 packages per hour 157,500 156,713 78 3,150 3,035-115 4251 133,000 134,330 1,330 2,660 2,821 (161) 49 101 94,500 85,050 9,450) ,890 1,804-86 35 20 (52) -15 Productivity Rate is calculated as follows: [Actual Volume/ (Actual Scheduled Hours Actual Overtime Hours)J. Differences in red parentheses highlight where Plan was not met

Explanation / Answer

Productivity rate = Actual volume / (Actual scheduled hrs. + Actual overtime hrs.)

Volume for the last 7 days was = 584,413

Forecast for next 7 days = 584,413 *(100% + 10%) = 642,854.3

Productivity rate will remain the same i.e. 47.3

So, if we assume overtime to be zero, the required scheduled hrs. = 642,854.3 / 47.3 = 13,591