MCT 451 Exam2 MULTIPLE CHONCE Choose the one alhermative that best complietes th
ID: 392564 • Letter: M
Question
MCT 451 Exam2 MULTIPLE CHONCE Choose the one alhermative that best complietes the statement or answers the question monhs of sales wene & 10. 15 and 9 units respectively. Suppose further 5) that the last our fonasts were 5& 11, and 12 units, respectively What is the Mean Absolute -30 5 Suppose that the last fo Deviation (MAD) of these forecasts? E) 2 D) 9 A) 105 5) 35 6) 6) Which of the following are among the 10 strategic operations L design of goods and services ll managing guality V marketing V. pricins of goods and services Gven an actual demand this period of 10a afrecast valr for thisperiod of 99, and an alpha of 7) what is the exponential smoothing forecast for next period? A) 974 B) 94.6 C1016 D) 103.0 E) 100.6 s) Gibson Valves produces cast bronne valves on an assembly line, currently producing 1600 valves 8) per shift. If the production is increased to 2000 valves per shift, labor productivity will increase by A) 10% B)50%. C)29% D)40%. E)20%. 9) John's House of Pancakes uses a weighted moving average method to forecast pancake sales. It assigns a weight of 5 to the previous month's demand, 3 to demand two months ago, and 1 to demand three months ago. If sales amounted to 1000 pancakes in May, 2200 pancakes in June, and 3000 pancakes in July, what should be the forecast for August? A) 2400 B) 2067 3767 D) 2511 E) 1622 10) A simple CM network has five activities,AB,CD,and EA is an immediate predecessor of C 10) and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Which of the following statements is true? A) There are two paths in this network B) There are five paths in this network There are four paths in this network D) There are six paths in this network E) There are 25 paths in this network 11) An activity on a PERT network has these time estimates optimistic-2, most likely 3, and pesimistic-8. What is its mectdactrity time and imine? A) 3.67; 1 B) 3.67,6 C)4.33; 1 D) 4.33;6 E) none of the aboveExplanation / Answer
5.
MAD = Sum of absolute values of differences between slaes and forecast / No. of periods
= I(8-5)I+I(10-6)I+I(15-11)I+I(9-12)I /4 = 14/4 = 3.5
B is correct.
6. I, II and III are operations management decisions. Marketing and pricing are not strategic operations management decisions. C is correct
7. Forecast for the next period
= forecast for the previous period + alpha ( sales for pervious period - forecast of pervious period)
= 99+0.4x( 103-99) = 100.6
E is correct.
8. Fraction Increase in productivity = 2000/ 1600 = 5/4 =1.25
Which means that there is 25% increase in productivity
C is correct.
9. Forecast = 5x3000+3x2200+1x1000 /9
= 15000+6600+1000/9
= 22600/9 = 2511.11
D is correct
10.
There are four paths in the network viz. ACE, BCE,BDE and ADE.
C is correct.
11. Here, Ta =2, Tm =3 and Tb =8
Expected duration = Ta+4Tm+tb / 6 = 22/6 =3.66
Variance = [Tb-Ta /6]2 = (6/6)2 =1
A is correct.