SM - Material Requirement Planning - MRP
XWF - 25 Points
Our strategy is to operate JIT. All suppliers are certified.
Suppliers are capable of delivering orders within 24 hours.
We operate 5 days per week; we shut down for 14 holidays.
Today marks the start of a 12-month production schedule.
Manufacturing requirement per year = 516,600 finished goods units of XWF; equal production scheduled for each work day; no seasonality.
Six (6) LBT assemblies are required for one (1) XWF
Requirements for each LBT assembly and the beginning inventories of each component:
3 of part #50; inventory = 89,000; 131,500 to be delivered in 24 hours
2 of part #60; inventory = 58,000; 39,000 to be delivered in 24 hours
8 of part #70; inventory = 120,000; 120,000 to be delivered in 24 hours
5 of part #80; inventory = 171,000; 280,000 to be delivered in 24 hours
Your job is to get components required to meet the production schedule. Factoring in the inventories and amounts on-order shown above, calculate:
1) The amount of each component needed to be purchased for week No. 1; a 5-day week, having no holidays.
2) The additional amounts of each component required for the next 8 weeks, a time period which includes 4 holidays.
3) The additional amounts of each component required for the balance of the year (beyond the 9 weeks above).
** Assume zero (0) component inventories at end of 12 months
** Assume no losses; 100% yield
DKI Oct 2016 copyright
Explanation / Answer
XWF parts to be manufactured per day = 516600/ ( 54x5-14) = 2018
LBT needed per week = 2018x6x5 = 12108x5 =60540
Part 50 needed = 3x60540 = 181620
First day's requirement will be fulfilled through inventory. The week's requirement will be done through additional inventory. No further purchase needed.
Part 60 needed = 2x60540 = 121080
Numbers needed to be purchased for the week = 121080 -( 58000+39000) =24080
Part 70 needed = 8x60540 =484320
Need to be purchased =484320- (240000) = 244320
Part 80 needed = 5x60540 =302700
Inventory available = 451000
Hence no need to purchase this part.
(2) LBT needed for the period = 2018x6x36 =435888
Total number of part 50 needed = 3x435888 =1307664
Parts previously left =38880
Numbers needed = 1268784
Number of part 60 needed = 2x 435888 =871776
There is no previously left part, so all have to be purchased.
Number of part 70 needed = 8x435888 = 3487104
There is no previously left part, so all have to be purchased.
Number of part 80 needed = 5x435888 =2179440
Previously left parts = 148300
Parts need to be purchased = 2179440-148300 = 2031140
(3) Rest of the year = 54-9 = 45 weeks having ( 14-4 =10) holidays
Number of workig days = 45x5 -10 = 215
Total production of XWF = 2018 x215 = 433870
Total number of LBT = 6x 433870 =2603220
Part 50 needed = 3x 2603220 =7809660
Part 60 needed = 2x2603220 =5206440
Part 70 needed = 8x2603220 = 20825760
part 80 needed = 5x 2603220 =13016100