Question
How do you disable Microsoft Project from rescheduling any unfinished work on tasks that contain some actual work? (This is a Microsoft Project Question)
A. File tab > Select Options > Select Schedule in Options dialog box > Uncheck “Split in-progress task” check box under Scheduling options for this project
B. Task tab > Tasks > Mode button > Select Auto Scheduled
C. Task tab > Tasks > Manually Scheduled button
D. File tab > Select Options > Selec t Schedule in Options dialog box > Uncheck “Tasks will always honor their constrain dates “check box under Scheduling options for this project
Explanation / Answer
To disable MS Project from rescheduling any unfinished work do the following, open File tab > Select Options > Select Schedule in Options dialog box > Uncheck “Split in-progress task” check box under Scheduling options for this project. Hence the correct option is A.