Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Project Management Class Hello I need help with the following assignment thank y

ID: 389274 • Letter: P

Question

Project Management Class

Hello I need help with the following assignment thank you in adavnce

Your University is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information Activity Predecessors None Duration (DAYS) Description Site Selection Buv Concessions Rent Facilities Build Stands Generator& Wiring Security Lighting Installation Sound System Stage Construction Tear Down B, C F,G 1. Conduct a forward and backward pass using Activity on the Node (AON) 2. Identify the total duration for the project. 3. Identify the Critical Path

Explanation / Answer

B F       

                                    H

A----- C--------E

                                G--------------------J

D                     I   

A) The estimated total duration for the project is 18 days .

B) The paths through the network include::

1) A-B-F-H-J:

2) A-C-E- H-J

3) A-C-E-G-J AND

4) A-D-I-J.

C) The critical path is A-b-f-h-j, containing no slack activities.