Progress Payment Calculations in Lump Sum Contract: Circle what is correct (Yes
ID: 388894 • Letter: P
Question
Progress Payment Calculations in Lump Sum Contract: Circle what is correct (Yes or No) (Y N) Documentation of a progress payment claim or request typically requires development of quantities placed. This may include survey data developed by a site survey team, documents from vendors indicating receipt and installation of material, invoices from subcontractors, and the like. (Y / N) If the contract is a lump or stipulated sum contract, then the quantities documented must be converted to a % complete of the total project. (Y / N) The assessment of % complete or % of work placed must be agreed to by both parties (i.e. client and contractor)Explanation / Answer
All three are correct.
Documentation of a progress payment claim or request typically requires development of quantities placed. This may include survey data developed by a site survey team, documents from vendors indicating receipt and installation of material, invoices from subcontractors, and the like.
If the contract is a lump or stipulated sum contract, then the quantities documented must be converted to a % complete of the total project.
The assessment of % complete or % of work placed must be agreed to by both parties (i.e. client and contractor)