Electronics Assembly Inc. is a contract manufacturer that assembles consurner electronics for a number of companies. Currently, the oprations manage The company wou'd assemble three models of cell phones in the same assembly cell. Selup time between the phones is negligible. Electronics Assembly Inc. operates two 8-hour shifts for 275 days per year. r is assessing the capacity requirements as input into a bid for a job to assemble cell phanes for a major global company. Demand Forecast Processing Time Cel Phone Mars Saturn Neptune 18,500 44.000 19.6 19.6 a. Calate total capacity required by line. b. Determine the total opcrating time availablk c. Calculate the tolal number of assembly cells. (Round up your answer to the next whole number.) cels

Explanation / Answer

Solution:

(a) Total capacity required by line is calculated as,

Total capacity required = (Demand forecast x Processing time) of each cell phone

Total capacity required = (33500 x 16.8) + (18500 x 19.6) + (44000 x 19.6)

Total capacity required = 1,787,800 minutes/year

(b) Total operating time available is calculated as,

Total operating time = 275 days/year x 2 shifts x 8 hours each x 60 minutes/hour

Total operating time = 264,000 minutes/year

(c) Total Number of assembly cells is calculated as,

Number of assembly cells = Total capacity required / Total operating time

Number of assembly cells = 1,787,800 / 264,000 = 6.77 or 7 (Rounding up to the next whole number)

Number of assembly cells = 7 cells