chose the correct answer ASAP if not sure don\'t, please! Q1-Project planning, a
ID: 3871114 • Letter: C
Question
chose the correct answer ASAP if not sure don't, please!
Q1-Project planning, an activity of a project manager, _____.
includes monitoring the progress of the a project, evaluating results, and taking corrective action when necessary to stay on target
involves requires guiding, supervising, and coordinating the a project team’s workload
focuses on long-term challenges and goals, the importance of stakeholders, and a commitment to the firm’s role as a corporate citizenconsists of staffing, which includes selecting the project team and assigning specific tasks to team members
d.includes identifying project tasks and estimating completion times and cost
Q2
includes informing management, users, and the project team about the progress of a project
includes identifying and arranging project tasks and estimating completion times and costs
involves the creation of a specific timetable, usually in the form of charts that show tasks, task dependencies, and critical tasks that might delay a project
consists of staffing, which includes selecting the project team and assigning specific tasks to team members
Q3
The first step in the creation of a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM) chart is to ____
identify all the project tasks
determine the logical order of project tasks identify
the graphical planning aids to use
determine the status of all tasks
a.includes monitoring the progress of the a project, evaluating results, and taking corrective action when necessary to stay on target
b.involves requires guiding, supervising, and coordinating the a project team’s workload
c.focuses on long-term challenges and goals, the importance of stakeholders, and a commitment to the firm’s role as a corporate citizenconsists of staffing, which includes selecting the project team and assigning specific tasks to team members
d.d.includes identifying project tasks and estimating completion times and cost
Q2
a.includes informing management, users, and the project team about the progress of a project
b.includes identifying and arranging project tasks and estimating completion times and costs
c.involves the creation of a specific timetable, usually in the form of charts that show tasks, task dependencies, and critical tasks that might delay a project
consists of staffing, which includes selecting the project team and assigning specific tasks to team members
Q3
The first step in the creation of a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM) chart is to ____
a.identify all the project tasks
b.determine the logical order of project tasks identify
c.the graphical planning aids to use
d.determine the status of all tasks
Explanation / Answer
Project manager has to plan
includes identifying project tasks and estimating completion times and cost
Project Manager reporting
includes informing management, users, and the project team about the progress of a project
The first step in the creation of a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM) chart is to
identify all the project tasks
Related Questions