Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, duratio
ID: 386659 • Letter: R
Question
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Immediate Time (weeks) Immediate Activity a b Predecessor(s)Activity a 10 24 18 10 bPredecessor(s) 4 2 C, E 12 14 D, G, H 20 C, E a) The expected (estimated) time for activity C is 12.50 weeks. (Round your response to two decimal places.) b) The variance for activity C is 2.25 weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is A-C-F- H -J K d) The estimated time for the critical path is 42.33 weeks. (Round your response to two decimal places.) e) The activity variance along the critical path is 11.72 weeks. (Round your response to two decimal places.) f) The probability that Hopkins Hospitality will finish the project in 42 weeks or less is (Enter as a probability and round your response to three decimal places.)Explanation / Answer
f) P(X<=42) = P(z)
where z = (T - E(t))/SQRT(2) = (42-42.33)/SQRT(11.72) = -0.0964
P(z) = 0.463 (approx)
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.