From the following list choose those elements that are involved in formal projec
ID: 3859108 • Letter: F
Question
From the following list choose those elements that are involved in formal project closure: (select all answers that apply)
Provide historical information for future projects
Host a post-project review
Pay project participants a bonus for any days ahead of schedule or dollars under budget
Close out contracts
Release project resources
Confirm and document whether project objectives were complete or not complete
Provide notice that the project documents were archived and will be kept for the period of time corporate policy dictates
A.Provide historical information for future projects
B.Host a post-project review
C.Pay project participants a bonus for any days ahead of schedule or dollars under budget
D.Close out contracts
E.Release project resources
F.Confirm and document whether project objectives were complete or not complete
G.Provide notice that the project documents were archived and will be kept for the period of time corporate policy dictates
Explanation / Answer
b. Host a post-project review
d. Close out contracts
e. Release project resources
f. Confirm and document whether project objectives were complete or not complete
g. Provide notice that the project documents were archived and will be kept for the period of time corporate policy dictates