| 15 of 23 (8 complete) Rogoreted before a training program of this nature could be conducted. The activities, immediate predeces Cinde is devetoping a program in supply chain management certification for managers. Ginde has listed a number of activities that must be Ginde has immediate predecessors, and times appear in the accompanying Activity Immediate Predecessorfo Time days) 2 5 10 5 5 A, D E. F This exercise contains only parts b, c, and d b) The critical activities for the leadership training program development project are B D E-G c) The project length for the leadership training program development project 28 days d) Slack time for each of the activities is: .. 11.1 ::Ja (1,1) -More Enter your answer in each of the answer boxes

Explanation / Answer

Calculate the ES, EF,LS,LF and Slack, as shown below:

Early start of A = 0 days

early finish of A = early start + activity time of A

early finish of A = 0 + 2 ( 2 days)

early start of B = 0

early finish of B = 5 days

Early start of C = 0

early finish of C = 2 day

early start of D = early finish of B ( 5 days)

early finish of D = 5 + 10 ( 15 days)

early start of E = maximum of early finish ( A,D)

early start of E = 15

early finish of E = 15 + 5 = ( 20)

early start of F = early finish of c ( 2)

early finish of F = 2+ 5 =( 6)

early start of G = maximum of early finish (E,F) 20 days

early finish of G = 20 + 8 ( 28 days)

latest finish of G = 28

latest start of G = latest finish - activity time

latest start of G = 28 - 8 ( 20 days)

latest finish of F = latest start of G ( 20)

latest start of F = 20 - 5 ( 15 days)

latest finish of E = latest start of G ( 20)

latest start of E = 20 - 5 ( 15 days)

latest finish of D = latest start of E ( 15)

latest start of D = 15 - 10 ( 5 days)

latest finish of C = latest start of F ( 15)

latest start of C = 15 - 2 = ( 13)

latest finish of B = latest start of D ( 5 )

latest start of B = 5 - 5 =( 0)

latest finish of A = latest start of E ( 15 days)

latest start of A = 15 - 2 ( 13)

Slack = Latest start - early start

Critical path where slack is zero. B-D-E-G. with duration 28 days