The manufacturing of a clock is comprised of six steps. Each step is staffed by
ID: 384871 • Letter: T
Question
The manufacturing of a clock is comprised of six steps. Each step is staffed by one worker. The table shows the tasks performed by each worker and the corresponding processing time: Step Tasks Processing Time seconds) 1. Heat-stake lens to bezel 2. Inspect bezel 3. Clean switch holes 4. Install set switch in bezel Preparation 26 18 68 Total time for A 23 12 25 60 5. Check switch travel Preparation 2 6. Clean Inslde bezel 7 Install module In bezel Total time for B 8. Install battery cllp on module 20 Battery Installation 9. Heat-stake battery clip on module20 10. Install two batterles In module 11. Check switch Total time for C 12. Install band 13. Inspect band Total time for D 45 Band Installation 14. Cosmetic inspection 4. 61 Packaging Preparation 15. Final test Total time for E 16. Place watch and cuff In display box 17. Place cover In display box base 20 14 30 Watch packaging 18. Place owner's manual and box Into tub Total time for F What is the labor content?Explanation / Answer
The Total Labour Content is sum of all effective time at all the difference steps:-
(68+60+70+58+65+64)=385 secs
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.