The manufacturing of a clock is comprised of slx steps. Each step is staffed by

ID: 384762 • Letter: T

Question

The manufacturing of a clock is comprised of slx steps. Each step is staffed by one worker. The table shows the tasks performed by each worker and the corresponding processing time: Tasks Processing Time 1 Heat-stake lens to bezel 2. Inspect bezel 3. Clean switch holes 26 Install set switch in bezel Total time for A 68 5. Check switch travel 6. Clean inside bezel 7. Install module in bezel Total time for B 23 25 60 8. Install battery clip on module 9. Heat-stake battery clip on module 10. Install two batteries in module 11. Check switch Total time for C Battery Installation 20 70 2. Install band 13. Inspect band Total time for D 58 14. Cosmetic inspection 15.Final test Total time for E Packaging Preparation 65 16. Place watch and cuff in display box 20 7, Place cover in display box base 8. Place owner's manual and box into 30 Watch packaging Total time forF What is the labor content?

Explanation / Answer

Total Labor content is sum of all effective time at all the different steps: 68+60+70+58+65+64= 385 secs