The computation of the duration of the network after ail logic is completed and
ID: 3835094 • Letter: T
Question
The computation of the duration of the network after ail logic is completed and all time estimates are included in the schedule requires a forward and backward pass (computation). These two functions results in sorting all activities into a forward group and a backward group generating the float (slack) on each activity and identifying the critical path generating a new logic for the schedule if it exceeds the desired time duration separating the critical path from the non-critical path activities in the networkExplanation / Answer
The computation of the duration of the networkafter all logic is completed and all time estimates are includedin the schedule requiresa forward and backward pass(computation). These two functions results in
Answer: generating the float (slack) on each activity and identifying the critical path
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.